The FINANCIAL — The construction of the New Safe Confinement at Chernobyl is entering its final stage. The giant structure has been erected over the past four years in a secure area near the damaged reactor in two separate pieces which are about to be joined together.
Meanwhile, a sophisticated ventilation system which will keep the structure corrosion-free during its lifespan is being installed and a technological building as the future control centre is under construction, according to EBRD.
Once all this is done, there is one remaining task before the finalisation of the project can begin: The New Safe Confinement will be fitted with fully-automated cranes, tools for deconstruction and other auxiliary systems. Once complete, in 2017 this new structure will be slid over the Chernobyl shelter that houses the reactor damaged in the 1986 nuclear accident.
The purpose of the New Safe Confinement – which will have a height of 110 metres, length of 165 metres and an arch span of 257 metres – is to protect the environment from radiation releases and provide the infrastructure to support the deconstruction of the shelter and nuclear waste management operations. The new structure has a lifespan of at least 100 years and will provide a timeframe within which to develop and implement mitigation strategies for dealing with the long-term legacy of the Chernobyl accident.
The New Safe Confinement is the central element of the Shelter Implementation Plan which sets out a roadmap for how to transform Chernobyl into a safe and secure state. Under the programme the shelter was stabilised, the site was cleared for construction of the New Safe Confinement and facilities were created to guarantee highest health and safety standards for the protection of the workforce on site.
During the peak period of construction about 1,200 workers from more than 27 nations are working on the site. They are regularly checked and the project has an excellent track record in terms of health and safety.
The total cost of the Shelter Implementation Plan is estimated at €2.15 billion, with the New Safe Confinement alone costing €1.5 billion. At present there remains a substantial funding gap which the international community, whose contributions the EBRD is administering as manager of the Chernobyl decommissioning funds, is aiming to close. The EBRD shareholders have committed €350 million from the Bank’s reserves in anticipation of a €165 million contribution from the G7/European Commission. The €100 million balance to close the financial gap is expected to be covered by non-G7/EC donors.
The work on reactor 4 is not the only task for the international community in Chernobyl: The three reactors which continued operations after the 1986 accident also need to be decommissioned, the spent fuel and radioactive waste treated and stored safely. For this purpose the international community is financing, through the Nuclear Safety Account, the Interim Storage Facility 2 (ISF2) at a cost in excess of €300 million and the Liquid Waste Treatment Facility (LRTP).
The ISF2 facility is currently in the final phase of construction and will process, dry and cut more than 20,000 fuel assemblies and place them in metal casks, which will be enclosed in concrete modules on site. The spent fuel will then be stored safely and securely for a minimum period of 100 years. The LRTP received an operating license at the end of 2014.